Taking in the new views (and buildings) at Cascade Campus

Photos and story by

Taking in the view from the rooftop of the new academic building at Cascade Campus.

Nick Hodges and Amie Bates with THA Architecture Inc. take in the new campus view looking east from the rooftop of the academic building.

September 10, 2013
Written by Gina Whitehill-Baziuk聽

This summer crews finished pouring and polishing all three concrete floors in the new academic building. They are now ready to聽begin exterior framing and mechanical and electrical work.

Construction on the new student center – just across the new campus plaza along N. Albina Avenue – 聽is following work on the academic building by about three months. 聽Crews have almost finished installing the metal decking, including the metal beam that campus and community members signed at the National Night Out event in early August. 聽The signed beam has been installed on the top floor facing Albina Avenue and can be seen from the sidewalk. Later this month, crews will pour the concrete floors.

The new academic building is going up fast - scheduled open for class in fall 2014.

Cascade Campus’ new academic building is going up fast – scheduled to open for classes next fall (2014).

Pacificmark, an聽MWESB firm, is doing聽the interior work for the student center, as a sub contractor for Hoffman.

The underground parking garage is nearly complete. 聽Hoffman crews finished the concrete walls in the garage and the ramp leading down to it this summer and are now working on mechanical and electrical rough-in and the stairwells leading to the new academic building and student center. 聽Contractors finished painting the garage ceiling white and will install interior later this fall.

小黄猫传媒鈥檚聽2008 voter-approved聽$374 million bond program is increasing opportunities for residents to access quality, affordable higher education close to where they live and work. Additional classrooms, updated equipment and technology, and advanced workforce training programs are helping聽to pave the way for future employment options. For more information, visit聽www.pcc.edu/about/bond/about.

The steel beam signed at the National Night Out event on August 8, hosted at Cascade Campus, is now installed on the top floor of the new student center.

The steel beam signed at the National Night Out event on August 8, hosted at Cascade Campus, is now installed on the top floor of the new student center.